Kenmore, Washington – Work for Kiewit General Manson (KGM) to construct the SR-520 Evergreen Floating Bridge Precast Deck Panels is finally complete.  Belarde Company Foreman, Desiree Orange and his crew began work on the project in October of 2014.  The deck panels will ultimately be the driving surface of the new bridge.   Each precast panel is 15’ x 56,’ requiring 46 cubic yards of concrete.  In total, 24,564 cubic yards of concrete was poured to manufacture 534 separate panels.  Construction of the panels took place at the KGM Kenmore Industrial Park.  Belarde crews built two to three panels per day over the course of nine months.

 

SR520 Crew 2